| February 1987 |
Technical Collaboration Agreement
signed between GNFC and Owens-Illinois Inc USA. |
| September 1989 |
Foreign Collaboration approved by
Govt of India |
| January 1991 |
Project implementation started. |
| July 1991 |
Videocon group join hands with GNFC
and assumes Management Control. |
| March 1994 |
Project completed and Plant commissioned. |
| February 1998 |
Obtained ISO-9002 certification
from Underwriters Laboratories Inc., USA. |
| September 1999 |
Panel “B” Furnace –
ground breaking |
| January 2002 |
Funnel Neck fabrication facility
commissioned. |
| June 2002 |
Mold Shop up gradation / modernization
completed. |
| January 2003 |
Started Export Business with Toshiba
– Indonesia |
| July 2003 |
Started Export Business with Thomson
- Poland |
| July 2003 |
Add. Panel Lines & Funnel Lines
Commissioned |
| Oct 2003 |
Obtained ISO 14001 & OHSAS 18001
Certifications. |
| Jan 2004 |
Panel “B” Furnace Electric
Boost started. |
| May 2004 |
Panel “A” Furnace Electric
Boost started. |
| Sep 2004 |
Plant -2 Ground Breaking |